Bahrain receives Bids for 100MW Al Dur Solar PV Power Stations

The Electricity and Water Authority (EWA), Bahrain receives Bidder Proposal to Establish Solar Power Stations at Al Dur area in the Southern Governorate of the Kingdom of Bahrain.

TBEA Xinjiang Sunoasis Company Limited has submitted the proposal. TBEA submitted the price of BHD 27.6 million (USD 73.4 million).

As per the tender notification,EWA stated that, the establishment of this project is in line with the National Goals of diversifying and sustaining energy resources for achieving the goals of the energy transformation plan in Bahrain.

The expected production capacity of the project is between 90 and 100 megawatts.

The tender for construction works of the Project will be implemented on Turnkey basis which includes Engineering, Design, Manufacturing, Supply of materials, Installation, Testing & commissioning and Civil & Electromechanical works as well as the connection of the stations to EWAs Electricity Transmission network.

The project implementation period is 18 months from the date of Award of the tender.