Ministry of Electricity & Water & Renewable Energy, Kuwait received bidders proposals for the Construction of Sabiya Combined Cycle Gas Turbine Power Plant (CCGT-4).
Two Bidders has submitted the proposals. Kuwait based Construction firm, Alghanim International General Trading and Contracting Company LLC has submitted the lowest bid.
Alghanim submitted the price of KWD 257.5million (USD 838.1 million).
Project Scope of Works includes the Supply, erection, Operation and Maintenance of the Combined Cycle Gas Turbine Power Plant by upgrading the Power Capacity at existing Sabiya Power & Distillation Plant by 900MW.
The Project will be constructed adjacent to existing Sabiya CCGT-3 located approximately 100km north of Kuwait City.
Project duration will be 36 months. Project Scope also includes complete operation and maintenance services for Seven (7) years.