Saudi Water Partnerships Company (SWPC) announced that it has successfully achieved financial close for three Independent Sewage Treatment Plants (ISTP) – Madinah-3 ISTP, Tabuk-2 ISTP and Buraydah-2 ISTP with the participation of success partners from the relevant authorities such as the Supervisory committee at the Ministry of Environment, Water and Agriculture, developers and consultants.
Madinah-3 ISTP:
Madinah-3 is an Independent Sewage Treatment Plant with capacity of 200,000 m3 per day with total cost around SAR 960 million, to be built and operated by the private sector for a period of 25 years from the Commercial Operation Date, noting that the winning consortium of the project consists of Acciona, Tawzea and Tamasuk.
Tabuk-2 ISTP:
Tabuk-2 is an Independent Sewage Treatment Plant with capacity of 90,000 m3 per day with total cost around SAR 550 million, to be built and operated by the private sector for a period of 25 years from the Commercial Operation Date, noting that the winning consortium of the project consists of Acciona, Tawzea and Tamasuk.
Buraydah-2 ISTP:
Buraydah-2 is an Independent Sewage Treatment Plant with capacity of 150,000 m3 per day with total cost around SAR 845 million, to be built and operated by the private sector for a period of 25 years from the Commercial Operation Date, noting that the winning consortium of the project consists of Acciona, Tawzea and Tamasuk.