Rabigh 3 Independent Water Plant Completes Reliability Test

SEPCO III, China announced in a statement that, the 30 day continuous reliability test of Saudi Arabia’s Rabigh Phase 3 Independent Water Plant was successfully completed and marking the successful completion of installation, commissioning and trail operation of the world’s largest single reverse osmosis seawater desalination project.

The Project officially entered the commercial operation stage.

The statement also mentioned that, the reliability test was began during November 2021 and was divided in to three phases, each lasting 10 days.

Under the witness of ACWA Power and Saudi Water Partnership Company , the performance reliability of each system of the project was tested in various operations modes with 80% and 100% load successfully.

The trail operation team composed of the multi-party consortium of the project monitored tens of the thousand of test data continuously throughout the whole process.

The 30-day reliability test was successfully completed at one time, 25 days ahead of the contract milestone point and all test indexes and parameters exceeded the contract standards, statement mentioned.

Read Also: Projects awarded during November 2021 in Gulf Countries