Saudi Electricity Company (SEC) received bidders proposals for 380kV Underground Cables Connection related to Integration of Shuaiba Solar PV Power Plant.
Five bidders has submitted the proposals. Saudi based construction firm, CEPCO has submitted lowest bid.
CEPCO submitted the price of SAR 42.48 million (USD 11.3 million).
Project scope of works includes Installation of 380kV Underground cables along with associated accessories. Project scope of works also includes the installation of 380kV Overhead transmission line (OHTL).
The project completion for the entire scope of work will be 20 months.