Trading Development Partnership (TDP) Company awarded the project, construction of 380kV Switching Substation, 9097. The Projects location is in Riyadh.
The Project was awarded by Saudi Electricity Company (SEC).
The value of the contract is SAR 287 million (USD 76.5 million).
Earlier, during February 2021, ten bidders has submitted the proposals. (read more)
The tender was issued by SEC during December 2020 (read more)
- 380kV Gas Insulated Switchgear (GIS)
- 380kV Hybrid GIS
- 13.8kV Switchgear
- 2.5MVA, 13.8kV/400V-230V Station Service Transformers
- 380kV, 120MVAR Reactors
- HV/MV Power Cables and Terminations,
- AC/DC Auxiliary Power Supply,
- Outdoor Switching equipment
- Control/Protection System,
- Substation Automation System (SAS)
- Communication System
- Fire Detection/Alarm and Safety and Fire Protection System
- Civil/Structural works and Mechanical works
- HCIS Security System
Project scope of work also includes the reinforcement of existing 9020 substation.
The Contractor shall perform on Lump sum turnkey basis, the design, engineering, materials procurement, quality management, factory inspection/testing, transport and delivery to site, installation, construction, site inspection, testing and commissioning, all associated work and services until final handing over of new substation work in a satisfactorily working and operating condition.
Contractor needs to achieve the final acceptance of the works by 27 months from Contract Signing Date.