Saudi Electricity Company announces the bid results for the construction of 380kV Double Circuit Overhead Transmission Line (OHTL) between Afif and Mahd Al Dahb in Central region of Saudi Arabia.
Eleven bidders has submitted the proposals. South Korea based construction firm, Hyundai Engineering & Construction (Hyundai) has submitted the lowest bid.
Hyundai submitted the price of SAR 296.3 million (USD 79million).
The tender was issued by SEC during May 2021 (read more)
Projects scope of works includes Construction of One (1) 380kV double circuit Overhead transmission line between New Afif BSP and Mahd BSP.
Approximate route length of OHTL is 219 km.
The project involves using of 4-795 kcmil ACSR/AW CONDOR conductor per phase and two (2) OPGW along the length of the new line.
The new OHTL will be installed on latticed steel tower in vertical configuration.
The Contractor shall perform on Lump sum turnkey basis, the design, engineering, materials procurement, quality management, factory inspection/testing, transport and delivery to site, installation, construction, site inspection, testing and commissioning, all associated work and services until final handing over of new OHTL work in a satisfactorily working and operating condition.
Contractor need to complete the project activities within 24 months from the date of contract award.
Read Also: Hyundai awarded $110 million contract for 380kV Hail Al Jouf OHTL