Saudi Electricity Company (SEC) awarded the project for construction of 380kV Double Circuit Overhead Transmission Line (OHTL) between Wadi Dawaser and Layla Project.
The Project has been awarded to Saudi based construction firm, National Contracting Company, NCC
The value of the contract is SAR 300,940,000 (USD 80,250,666).
SEC received bidders proposals, during October 2020 (read more)
The project involves the design and construction of two (2) 380kV OHTL to connecting the Wadi Dawaser BSP and Layla BSP In central region of Saudi Arabia
Approximate route length of OHTL is 293.25 km.
The project involves using of 4-795 kcmil ACSR/AW CONDOR conductor per phase and two (2) OPGW along the length of the new line.
The new OHTL will be installed on latticed steel tower in vertical configuration.
The Contractor shall perform on Lump sum turnkey basis, the design, engineering, materials procurement, quality management, factory inspection/testing, transport and delivery to site, installation, construction, site inspection, testing and commissioning, all associated work and services until final handing over of new OHTL work in a satisfactorily working and operating condition.
Contractor need to complete the project activities within 28 months from the date of contract award.
In another contract, NCC awarded the Reinforcement of 380kV Layla Substation. The value of contract is SAR 33.5 million (USD 8.9 million).
***