PA Cost International signed a EPC contract for the “Construction of 115/13.8KV Urairah Substation & Connection” with Saudi Electricity Company (SEC).
The Project location will be in Urairah, Eastern Region of Saudi Arabia. The tender was opened during October 2020 (read more)
The value of signed contract is SAR 51,890,000 (USD 13,837,333).
115/13.8kV Substation, Urairah:
Project involves the construction a new indoor 115/13.8kV Gas Insulated Substation in Urairah with the following major equipment
- 115kV Gas Insulated Switchgear (GIS)
- 50/67 MVA, 115/13.8kV Power Transformers – Supplied by SEC
- 13.8 Switchgear
- 13.8kV Shunt Capacitor Filter Bank
- 500kVA, 13.8kV/400V-230V Station Service Transformers
- Advance Metering Infrastructure (AMI) System
- HV/MV Power Cables and Terminations,
- AC/DC Auxiliary Power Supply,
- Surge Arresters
- Control/Protection System,
- Substation Automation System (SAS)
- Communication System
- Fire Detection/Alarm and Safety and Fire Protection System
- Civil/Structural works and Mechanical works
- Security System
- Retrofitting of Overhead Transmission line (OHTL)
The Contractor shall perform on Lump sum turnkey basis, the design, engineering, materials procurement, quality management, factory inspection/testing, transport and delivery to site, installation, construction, site inspection, testing and commissioning, all associated work and services until final handing over of new substation works in a satisfactorily working and operating condition.
Contractor need to achieve the final acceptance of the work within 27 months from the awarded date of contract.
***
For latest updates, follow us on LinkedIn, Facebook, Twitter,