Oman received the lowest bid of $61 million for Duqm Dual Carriageway Road

Special Economic Authority of DUQM, Oman announces the bid results for the project, Construction of Dual Carriageway Road for NR 32 Phase 2 at Duqm.

The project location is in Al Duqm Waliyat of Al Wusta governate.

Fourteen bidders has submitted the proposals. Oman based constraction firm, Premier International Projects submitted the lowest bid.

The contractor submitted the price of OMR 23,485,850 (USD 61,081,534)

The tender was issued during August 2020 (read more)

Scope of work includes, construction of approximately 12 km of dual-carriageway starting from the end station of NR 32 Phase 1 until the end border of Duqm Authority including 2 Roundabouts, wadi Bridge, 1 km single carriageway service Road.

The main components of the project are as follows

  • Construction of approx. 12 km of dual carriageways having. 3 lanes on each carriageway with a 12m unpaved median.
  • Approx. 1 km service roads in front of Existing Filling Station.
  • Two Roundabouts
  • One wadi Bridge
  • Culverts and drainage catch pits,
  • LED street lighting,
  • Landscaping.
  • Relocation & protection of existing utilities and other ancillary works.
  • Weigh Station (Optional)

Read Also: Oman awards $62.1 million road contract at Duqm

***

For latest updates, follow us on  LinkedInFacebookTwitter, Instagram , PinterestYouTubeTumblr, Google News