GE secured long-term maintenance contract for Kuwait substations

GE Renewable Energy’s Grid Solutions announced in a statement that it has secured long-term maintenance contract of 54 substations located across the Kuwait.

The project was awarded by Ministry of Electricity & Water, Kuwait.

The 54 substations of different voltage levels including 132 and 300 KV, will be maintained by GE’s Grid Solutions  by ensuring planned maintenance and emergency intervention for smooth operation.

The duration of the contract is five years.

As per the statement, this is the largest contract of its kind and underlines the in-country strength of GE’s Grid Services to meet the requirements of the Ministry in maintaining the operational efficiency of its electricity infrastructure.

Awarding the contract to GE also builds on the company’s proven track-record of successfully delivering a similar three-year contract, signed in 2016, with the Ministry of Electricity & Water for the inspection, state-of-the-art testing, repair, total maintenance and supply of spares for 54 GIS.

GE has delivered several key services contracts in Kuwait, including the first asset performance management solution including dissolved gas analysis (DGA) monitoring the health condition of a transformer fleet for the Ministry as well as deployed digital services to modernize the country’s grid infrastructure.

***

For email notifications regarding our updates, please subscribe us.

For latest updates, follow us on  LinkedInFacebookTwitter, Instagram , PinterestYouTubeTumblr

1 Trackback / Pingback

  1. Projects awarded during November 2020 in Gulf Countries