Saudi Electricity Company (SEC) announces the bid results for the project “Construction of 115/13.8KV Urairah Substation & Connection”
The Project locations will be in Urairah, Eastern Region of Saudi Arabia.
Saudi based Construction Company, PA Cost International, a subsidiary of ORA Holding Group has submitted the lowest bid.
PA Cost submitted the price of SAR 51,890,000 (USD 13,837,333).
115/13.8kV Substation, Urairah:
Project involves the construction a new indoor 115/13.8kV Gas Insulated Substation in Urairah with the following major equipment
- 115kV Gas Insulated Switchgear (GIS)
- 50/67 MVA, 115/13.8kV Power Transformers – Supplied by SEC
- 13.8 Switchgear
- 13.8kV Shunt Capacitor Filter Bank
- 500kVA, 13.8kV/400V-230V Station Service Transformers
- Advance Metering Infrastructure (AMI) System
- HV/MV Power Cables and Terminations,
- AC/DC Auxiliary Power Supply,
- Surge Arresters
- Control/Protection System,
- Substation Automation System (SAS)
- Communication System
- Fire Detection/Alarm and Safety and Fire Protection System
- Civil/Structural works and Mechanical works
- Security System
- Retrofitting of Overhead Transmission line (OHTL)
The Contractor shall perform on Lump sum turnkey basis, the design, engineering, materials procurement, quality management, factory inspection/testing, transport and delivery to site, installation, construction, site inspection, testing and commissioning, all associated work and services until final handing over of new substation works in a satisfactorily working and operating condition.
Contractor need to achieve the final acceptance of the work within 27 months from the awarded date of contract.
***