NCC submits lowest bid of $80.2 million for 380kV OHTL Project

Saudi Electricity Company announces the bid results for the construction of 380kV Double Circuit Overhead Transmission Line (OHTL) between Wadi Dawaser and Layla Project.

Ten bidders has submitted the proposals. Saudi based construction firm, National Contracting Company, NCC has submitted the lowest bid.

NCC submitted the price of SAR 300,940,000 (USD 80,250,666)

The project involves the design and construction of two (2) 380kV OHTL to connecting the Wadi Dawaser BSP and Layla BSP In central region of Saudi Arabia

Approximate route length of OHTL is 293.25 km.

The project involves using of 4-795 kcmil ACSR/AW CONDOR conductor per phase and two (2) OPGW along the length of the new line.

The new OHTL will be installed on latticed steel tower in vertical configuration.

The Contractor shall perform on Lump sum turnkey basis, the design, engineering, materials procurement, quality management, factory inspection/testing, transport and delivery to site, installation, construction, site inspection, testing and commissioning, all associated work and services until final handing over of new OHTL work in a satisfactorily working and operating condition.

Contractor need to complete the project activities within 28 months from the date of contract award.

Earlier, during December 2019, NCC awarded an order of $87.2 million for construction of 380kV Transmission line between Layla and Al Kharj (read more)

***

For email notifications regarding our updates, please subscribe us.

For latest updates, follow us on  LinkedInFacebookTwitter, Instagram , PinterestYouTubeTumblr
For Advertise or Sponsorship,  pleas visit “Advertise” Page.

1 Trackback / Pingback

  1. NCC awarded $89million 380kV OHTL and Substation Project

Comments are closed.