Saudi Electricity Company announces the bid results for the construction of 380kV Double Circuit Overhead Transmission Line (OHTL) between Arar and Rafha Project.
A total of ten bidders has submitted the proposals. India based construction firm, Larsen & Toubro Limited (L&T) has submitted the lowest bid.
L&T submitted the price of SAR 338,500,000 (USD 90,266,666)
The project involves the design and construction of two (2) 380kV OHTL to connecting the Arar BSP and Rafha BSP In Northern region of Saudi Arabia
Approximate route length of OHTL is 334.70 km.
The project involves using of 4-795 kcmil ACSR/AW CONDOR conductor per phase and two (2) OPGW along the length of the new line.
The new OHTL will be installed on latticed steel tower in vertical configuration.
The Contractor shall perform on Lump sum turnkey basis, the design, engineering, materials procurement, quality management, factory inspection/testing, transport and delivery to site, installation, construction, site inspection, testing and commissioning, all associated work and services until final handing over of new OHTL work in a satisfactorily working and operating condition.
Contractor need to complete the project activities within 24 months from the date of contract award.
Earlier, during September 2020, L&T submitted lowest bid of $88.7 million for Rafha and Qaisumah 380kV OHTL Project. (read more)
***