Saudi Electricity Company announces the bid results for the construction of 380kV Double Circuit Overhead Transmission Line (OHTL) between Khafji and Nariyah in eastern region of Saudi Arabia.
Ten bidders has submitted the proposals. Saudi based construction firm, Al Haider for Trading and Contracting (Al Haider) has submitted the lowest bid.
Al Haider submitted the price of SAR 126,490,000 (USD 33,730,666).
The tender was issued by SEC during September 2020 (read more)
The project involves the design and construction of two (2) 380kV OHTL to connecting the Khafji BSP and Nariyah North BSP
Approximate route length of OHTL is 130 km.
The project involves using of 4-795 kcmil ACSR/AW CONDOR conductor per phase and two (2) OPGW along the length of the new line.
The new OHTL will be installed on latticed steel tower in vertical configuration.
The Contractor shall perform on Lump sum turnkey basis, the design, engineering, materials procurement, quality management, factory inspection/testing, transport and delivery to site, installation, construction, site inspection, testing and commissioning, all associated work and services until final handing over of new OHTL work in a satisfactorily working and operating condition.
Contractor need to complete the project activities within 27 months from the date of contract award.
***