SEC invite tender for 130km of Khafji-Nariyah 380kV OHTL Project

Saudi Electricity Company invites bid for the construction of 380kV Double Circuit Overhead Transmission Line (OHTL) between Khafji and Nariyah in eastern region of Saudi Arabia.

The project involves the design and construction of two (2) 380kV OHTL to connecting the Khafji BSP and Nariyah North BSP

Approximate route length of OHTL is 130 km.

The project involves using of 4-795 kcmil ACSR/AW CONDOR conductor per phase and two (2) OPGW along the length of the new line.

The new OHTL will be installed on latticed steel tower in vertical configuration.

The Contractor shall perform on Lump sum turnkey basis, the design, engineering, materials procurement, quality management, factory inspection/testing, transport and delivery to site, installation, construction, site inspection, testing and commissioning, all associated work and services until final handing over of new OHTL work in a satisfactorily working and operating condition.

Contractor need to complete the project activities within 27 months from the date of contract award.

Present Bid submission date is 27 October 2020.

Presently SEC issued tenders for a route length of more than 1500km of 380kV OHTL projects. (read more)

***