Saudi Electricity Company, SEC invites bids for the construction of 380kV Double Circuit Overhead Transmission Line (OHTL) across Saudi Arabia.
At present, tender floated for a total route length of 1036.58 km.
The SEC OHTL lines are interconnecting Arar, Rafha, Qaisumah, Hail and Al Jouf areas.
OHTL between Hail and Al Jouf:
The project involves the design and construction of two (2) 380kV OHTL to connecting the Hail 3 BSP 9039 and Al Jouf 1 BSP.
Approximate route length of total OHTL route is 374.95 km.
The project involves using of 4-795 kcmil ACSR/AW CONDOR conductor per phase and two (2) OPGW along the length of the new line. (read more)
Contractor need to complete the project activities within 24 months from the date of contract award.
At present Bid Submission date is 03 September 2020.
OHTL between Arar and Rafha:
The project involves the design and construction of two (2) 380kV OHTL to connecting the Arar 380/132kV BSP and Rafha 380/132kV BSP.
Approximate route length of total OHTL route is 334.70 km.
The project involves using of 4-795 kcmil ACSR/AW CONDOR conductor per phase and two (2) OPGW along the length of the new line.
Contractor need to complete the project activities within 24 months from the date of contract award.
At present Bid Submission date is 07 October 2020.
The project involves the design and construction of two (2) 380kV OHTL to connecting the Rafha 380/132kV BSP and Qaisumah BSP.
Approximate route length of total OHTL route is 326.93 km.
The project involves using of 4-795 kcmil ACSR/AW CONDOR conductor per phase and two (2) OPGW along the length of the new line.
Contractor need to complete the project activities within 24 months from the date of contract award.
At present Bid Submission date is 17 September 2020.
***