As per the terms of the project, contractor will execute the works on lump sum turnkey basis for Engineering, Procurement and Construction for the Rehabilitation of 110/13.8kV Substation that was burnt due to fire incident.
Existing available Gas Insulated Switchgear and Power Transformers will be utilized for this project.
The project scope of works includes 13.8kV Switchgear, Protection & Control System, Substation Automation System, Telecom System, Civil Works and Electro-Mechanical Works.
Contractor needs to achieve the final acceptance of the works by 24 months from Contract Signing Date.
Siemens Energy announced in a statement that it was selected to supply new electric motor driven compressors for Saudi Aramco’s Tanajib Plant facilities. The company …
Antaisolar and Bahra Electric have reached an agreement to establish a joint venture (JV) company and factory in Jeddah, SaudiArabia. It marks a milestone in …
His Royal Highness Crown Prince Mohammad bin Salman bin Abdulaziz, Prime Minister and Chairman of the Public Investment Fund (PIF) announced today the Diriyah Project …
1 Trackback / Pingback
Comments are closed.