Saudi Electricity Company (SEC) announces the bid results for the project “Installation of 380kV reactors at Madain Substation”.
The Project location is in Al Ula, Northern region of Saudi Arabia.
A total of five companies has submitted the proposals. Saudi based construction Company, National Contracting Company (NCC) submits the lowest bid.
NCC has submitted the price of SAR 25,720,000.
Installation of 380kV reactors at Al Ula:
Project scope of work involves the installation of two (2) 380kV Bus connected Reactors at the existing Madain BSP.
It includes protection, control, communication and SAS/SCADA systems. The BSP shall be equipped with IEC 61850 standards based technically and economically optimized Substation Automation System (SAS) and will be remotely controlled from the SEC Power Control Center (PCC) through SCADA and Communication.
Major equipment includes two (2) 380kV, 60MVAR Bus connected Reactors, two (2) 380kV Hybrid GIS, modification on AC/DC, LV auxiliary supply, protection, metering, control SCADA & telecommunication, civil and electromechanical works.
The Contractor shall perform on Lump sum turnkey basis, the design, engineering, materials procurement, quality management, factory inspection/testing, transport and delivery to site, installation, construction, site inspection, testing and commissioning, all associated work and services until final handing over of substation works in a satisfactorily working and operating condition.
Contractor need to achieve the final acceptance of the work within 17 months from the date of contract signed.
Read Also: L&T Signed the High voltage switchgear and Reactors project in Saudi Arabia
***
In order to receive email notifications regarding our updates, please subscribe us.
1 Trackback / Pingback
Comments are closed.