Saudi Electricity Company (SEC) issued a tender for the “Construction of 380kV Transmission line between Al Aseelh (ASL) 380/132/13.8kV BSP and Shuqaiq Substation”.
The location of the project is in Jazan, Southern region of Saudi Arabia.
Al Aseelh-Shuqaiq 380kV Transmission Line:
This project involves the design and construction of two (2) 380kV OHTL to connect the Al Aseelh (ASL) 380/132/13.8kV BSP.
Approximate route length of total OHTL route is 140.2 km.
Once the project completed, Al Aseelh substation will be connected to the network through Shuqaiq Substation.
The project involves using of 4-795 kcmil ACSR/AW CONDOR conductor per phase and four (4) OPGW along the length of the new line.
The Contractor shall perform on Lump sum turnkey basis, the design, engineering, materials procurement, quality management, factory inspection/testing, transport and delivery to site, installation, construction, site inspection, testing and commissioning, all associated work and services until final handing over of new OHTL work in a satisfactorily working and operating condition.
Contractor need to complete the project activities within 25 months from the date of contract award.
At Present, the bid opening date is 26 March 2020.
Read Also:
- NCC submits the lowest bid of $60.8 million for 380kV Substation in South region
- Saudi Electricity Company issued a new tender for 380kV Transmission line at Al Aseelh
***
In order to receive email notifications regarding our updates, please subscribe us.