NCC awarded an order of $87.2 million for Saudi Arabia’s 380kV Transmission line between Layla and Al Kharj

Saudi Electricity Company (SEC) awarded the project “Construction of 380kV & 132kV Overhead Transmission line interconnection of Layla 9049 BSP”

The interconnection of the project is between Layla & Al Kharj area, central region of Kingdom of Saudi Arabia.

The project has been awarded to Saudi based construction company, National Contracting Company (NCC), a subsidiary of Rezayat Group.

The value of signed contract is SAR 327 million (1$=3.75SAR)

Earlier, during July 2019, a total of twelve (12) bidders has been submitted the proposals. After technical and commercial evaluation, the project has been awarded to contractor.

Project Description:

Saudi Electricity Company intends to interconnect its new 380kV Substation, 9049 with the National Grid via 380kV and 132kV overhead transmission line.

Scope of work includes design, supply, installation, testing & commissioning of 380kV Double Circuit Transmission line of approximate route length 300km between Layla and Al Kharj Region.

Scope of work also includes design, supply, installation, testing & commissioning of 132kV Transmission line of approximate route length 34km along with associated 132kV underground cables.

132kV, 1200 Sq.mm Underground cable of approximate route length 3.5km is part of the Scope of Work.

The contractor shall perform the project on lumpsum turnkey basis, includes the design, engineering, material procurement, quality management, factory inspection/testing, transport and delivery to site, construction, site inspection, testing and commissioning, and all associated work and services until final handing over of the project.

Contractor need to achieve the final acceptance of the work within 27 months from the awarded date of contract.

Read Also: NCC submits the lowest bid of $60.8 million for 380kV Substation in South region