Capital Lights Company submits the lowest bid for 115kV Cable Project in Al Hassa

Saudi Electricity Company (SEC) announces the bid results for the “Installation of 115kV Underground cable for the integration of Al Hassa Housing 115/13.8 kV substation”

The project location is in Al Hassa, eastern region of Saudi Arabia.

A total of sixteen (16) bidders has submitted the proposal. Saudi based Construction Company, Capital Lights Co. For Electro-Mechanics (Capital Lights ) has submitted the lowest bid.

Capital Lights Submitted the price of SAR 35,952,000 (1$=3.75 SAR)

Project Description:

Project Scope of work includes Design, supply, testing, commissioning and installation of two (2) 115kV Underground cable circuits, consisting of one (1) 1x1Cx1200 Sq.mm mm, Cu conductor, super clean-XLPE, Cu metallic sheath, cable per phase complete with all other accessories, from Al-Daeree 380/230/115kV BSP to Al-Hassa Housing 115/13.8kV Substation.

The length of each circuit shall be approximately 9.93 km.

Design, supply and installation of approximately 9.93 km of 1×96 cores Non-Metallic Underground Fiber Optic cables along the new 115kV Power Cables route is part of the project.

The Contractor shall perform on Lump sum turnkey basis, the design, engineering, materials procurement, quality management, factory inspection/testing, transport and delivery to site, installation, construction, site inspection, testing and commissioning, all associated work and services until final handing over of new cable work in a satisfactorily working and operating condition.

Contractor needs to achieve the final acceptance of the works by 23 months from Contract Signing Date.

***