Saudi Electricity Company announces the bid results for the project “Construction of Layla (9049) 380/132kV BSP and Installation of One (1) 380kV, 60MVAR Line Reactor at 9028 BSP”.
The location of the project is in Layla area, central region, around 300km from Capital City, Riyadh
A total of eleven (11) bidders has been submitted the proposals. Chinese Construction Company, SEPCO III Electric Power Construction, has submitted the lowest bid.
SEPCO III quoted the price of SAR 203.5 million (1$=3.75 SAR)
Project Description:
Saudi Electricity Company intends to build new 380kV Substation in layla area to meet the rapidly growing power supply demand.
Scope of Work includes design, supply, installation, testing & commissioning of 380kV Gas Insulated Switchgear (GIS), 132kV GIS, 380kV Hybrid GIS, Transformers (502.5 MVA, 380/132/13.8kV), Reactors (380kV, 120MVAr and 132kV, 40MVAr), complete protection, metering, control, communication and SCADA equipment, Civil and Electro-Mechanical Works. The new Substation shall be equipped with Substation Automation System (SAS)
The contractor shall perform the project on lumpsum turnkey basis, includes the design, engineering, material procurement, quality management, factory inspection/testing, transport and delivery to site, construction, site inspection, testing and commissioning, and all associated work and services until final handing over of the project.
Note: For complete scope of work or other information, please do contact us.
Read more: Saudi Arabia announces the new 380kV Substation tender for Central Region