06-May-2019, Riyadh:
Saudi Electricity Company issued new tender for “Construction of New Marjan 380/230kV BSP and Construction of 230kV Underground Cables”.
Once the project completed, it will feed the power to Saudi Aramco’s under development project, called Marjan Field Development Project in Tanajib area, eastern region of Kingdom of Saudi Arabia.
Scope of Work includes design, supply, installation, testing & commissioning of 380kV GIS, 230kV GIS, 452.5/602.5/752.5 MVA Auto transformers, 13.8kV Switchgear, Protection & Control System, Substation Automation System, Telecommunication System and other auxiliaries.
Project works also includes 230kV, 2500 Sq.mm Cable of approximate route length 1 km and a total of three (3) Circuits will be constructed between new substation and Saudi Aramco’s Gas plant.
Bid Submission date is on 30-June-2019
Note: For more details, please contact us.
When the project will sign