11-Ap-19:Riyadh
Saudi Electricity Company awarded the project “Expansion of Qassim-2 (9025) 380/132kV BSP. The Project has been signed by (please subsribe to view more details) construction company
Earlier, during November 2018, techno-commercail offers was submitted by EPCs.
The value of the contract is SAR 84.7 million (1$=3.75 SAR)
The Scope of Work includes expansion of existing 380kV GIS with Two Diameters, GIS/GIB modifications as a result of swapping of OHTLs, Construction of new gantries for spare OHTL and installation of TWO Line Reactors for new 380kV OHTL between Madinah East BSP and 9025 BSP. The project also cover necessary modifications in GIS/ GIBs for installation of above mentioned line reactors, protection, communication, metering and SCADA/ SAS works
The project is located in Qassim area, Central region of Kingdom of Saudi Arabia. This project has been created to construct the second interconnection between Qassim and Madinah.
Total duration of project is 25 months.