Saudi Utility Company awarded the 380kV Substation

25-Mar-2019:
Riyadh:
 
Saudi utility Company, (Please contact us to view company name) Signed the contract for the project “Design and Construction of Substation 16P”
 
German based Company (Please Subscribe) has been awarded the contract.
 
The location of Substation is in Yanbu, Western region of Kingdom of Saudi Arabia. The voltage levels of the substation are 380/115/34.5kV.
 
 
 Earlier a total of eight (8) bidders has submitted their proposal.
 
(Please contact us to view company name) has quoted the price of SAR 248.2million (1$=3.75 SAR).
 
Project Description:
 
The Engineering, Procurement and Construction (EPC) contract to provide a complete and functional electrical power system installation in Madinat Yanbu Al-Sinaiyah (MYAS) comprising but not limited to: Five bays of 380kV Gas Insulated Switchgear (GIS), Six bays of 115kV GIS, two (2) numbers 300/400/500MVA, 380/115kV Power Transformers, three (3) numbers of 100/125MVA, 115/34.5kV Transformers, 34.5kV Switchgear
 
The period of performance is One Thousand and Ninety-Five (1095) days.
 
Note: Please contact us for complete information.