The value of the project is 189.85 million Saudi Riyals (1$=3.75 SAR)
This project covers the construction of a new indoor type 380/115kV GIS Substation named as EIC 380/115kV BSP with the related works in connection with the Metering, Protection, Control and Communication. The new Substation shall be equipped with Substation Automation System (SAS) and will be remotely controlled from the Power Control Center (PCC to be constructed by Saudi Aramco), through SCADA system, Communication System and gateway.
The monitoring, Control and Protection system shall be as per IEC 61850 Standard based on Substation Automation System. The substation shall be provided with “Class-C” facility. All polices of SEC 5-Star safety and Health Management System shall be implemented in this project.